GAO: Columbia-Class Schedule And Cost Growth Likely To Increase, Navy Should Revise Cost Estimates

GAO: Columbia-Class Schedule And Cost Growth Likely To Increase, Navy Should Revise Cost Estimates
General Dynamics Electric Boat conducted a keel laying ceremony for the first Columbia-class ballistic missile submarine, USS District of Columbia (SSBN-826) at Quonset Point, Rhode Island, June 4, 2022. (Photo: U.S. Navy)

The Government Accountability Office’s (GAO) latest audit of the Columbia-class nuclear ballistic missile submarine program estimated the first new boat has cost overruns several times higher than the shipbuilder and Navy estimates, so the service needs to review cost estimates. In April, the Secretary of the Navy’s 45-day shipbuilding review found significant delays in major programs, including how the lead submarine, the future USS District of Columbia (SSBN-826), is running 12 to 16 months behind schedule (Defense Daily, April 3).…

Subscriber-only content. Please log in below.

Not a subscriber or registered user yet?

Please contact us at clientservices@accessintel.com or call us at 888-707-5814 (Monday – Thursday 9:00 a.m. – 5:30 p.m. and Friday 9:00 a.m. – 3:00 p.m. ET.), to start a free trial, get pricing information, order a reprint, or post an article link on your website.



Congress Updates

Lawmakers Request DoD Briefing On Army’s Planned Cuts To Aviation Procurement

A bipartisan group of House lawmakers has sent a letter asking the Pentagon for a briefing on the potential industrial base impacts as a result of the Army’s planned cuts […]


CENTCOM Looking To Lessons Learned From Use Of LUCAS Drones

U.S Central Command (CENTCOM) is looking to lessons learned from its use of Low-cost Unmanned Combat Attack System (LUCAS) drones by Phoenix-based SpektreWorks, according to CENTCOM head Adm. Brad Cooper. […]


Hegseth Says DoD Open To Reviewing Army’s Planned Cuts To Legacy Helicopter Procurement

Defense Secretary Pete Hegseth has told lawmakers the Pentagon is open to reviewing the Army’s planned procurement cuts to its legacy manned aviation fleet. Rep. Rosa DeLauro (D-Conn.), ranking member […]


Appropriators Press For Details On Iran War Costs; DoD’s $29B Estimate Doesn’t Include Base Damage

The Pentagon estimates the U.S.’ ongoing conflict with Iran has now cost at least $29 billion, while a lead official noted the updated figure does not factor in damage to […]